Wednesday, June 15, 2005

ODOT 156 06.15.2005

Bridge Steel was set last week. Steel Erector has finished bolting the
structure up. Would like to continue working night shift next Monday
evening through next Thursday evening. LEOs will again be required.

Forming of backwall is progressing -- issues are open.

Field visit is required.